TRICK–1 : Men–Days–Work (Basic Rule)


Rule


Men × Days = Constant Work 


Ex 1. 12 men can do a work in 20 days. How many days will 5 men take ?


Soln


12×20 = A


A = 240/55 = 48


Ans: 48 days


Ex 2. 15 boys can do a work in 20 days. How many days will 10 boys take? (Boys Problem)


Soln


15×20 = 10 × A


Ans: 30 days


TRICK–2 : Men–Women–Work


Rule: First convert all workers into one unit using efficiency.


Ex 3. 1 Man = 2 Women, 5 men + 4 women can do work in 36 days. How many days will 4 men take ?


Soln


5M + 4W = 5M + 2M = 7M


7 × 36 = 4 × A


Ans: 63 days


TRICK–3 : Efficiency ↔ Time


Rule: Efficiency 1/Time


Ex 4. Efficiency of A : B = 3 : 2 Find time ratio.


Soln


Time = 2:3


Ans: 2 : 3


TRICK–4 : Wages & Efficiency


Rule: Wages Efficiency


Ex 5.  A, B, C complete a work together. Efficiency ratio = 15 : 12 : 10.Total wages = ₹7400. Find B’s share.


Soln


Total ratio = 15+12+10 = 37


B = 12/37×7400


B = ₹2400


Ans: ₹2400


TRICK–5 : Given Time of Each, Find Wages


Ex 6.  A works 15 days, B works 12 days, C works 10 days. Total wages = ₹7400. Efficiency same.


Soln


Ratio = 15:12:10


Sum = 37


A = 15/37×7400=₹3000


Ans: ₹3000